|
|
|
|
|
 |
|
Developing Our New Track Site - The Diary.
|
|
 |
2010 - The Final Touches ?
This is a summary of work done in the current year; please select from the Year tabs above to follow progress in other years.
A work of this size is a huge undertaking for a small group, and I hope you will look back through the previous year tabs to get a flavour of what has been achieved.
- - - - -
Surviving a harsh winter without incident, the design and build of the track has stood up well, and credit must go to those who have had a hand in making a superb job of the track and supporting infrastructure.
Things have come a long way since the low times around the turn of the century, when vandalism was taking away the enjoyment of our hobby, but our new track and site have set the Society up well for the future.
And positively, membership has definitely increased, from 38 members in 2001 to over double that today.
There are still a number of important tasks to complete, and hopefully most will be tackled through this year.
Our construction diary is in the adjacent column . . .   - most recent item at the top.
Please hover your mouse over photos for a description.
|
 |
|
 |
Building Bridges.                               23th May 2010

Work is now underway on the footbridge from the parking area.  Off-site Kevin has welded up the new frame that forms the 3M walkway from the end of the steps.  On Sunday morning Kevin and Ted drilled 5 holes in the steps section to allow the extension to be bolted on. A new cutter guard made by John W has been fitted as part of ride on mower's winter overhaul, which is now running very well.
New 7¼" Bays, and Cat Flaps.                   15th April 2010

Continuing the upgrades to the steaming bays, the two mixed 3½/5" gauge bays have been modified by the insertion of a welded 'cat flap'.  A section of the 3½" gauge rail can now be swung out of the way to allow a 5" gauge loco grate to drop straight through.  A simple catch allows the rail to be secured back in place for normal use with a 3½" gauge loco.

The final job in the steaming bay area was the fitting of an extra pair of rails to two of the bays forming dual gauged bays that will take 7¼" gauge locomotives. As part of the traverser upgrade, all steaming bays have been moved slightly away from the traverser and realigned, losing their 'wonky' look, and are now visually more pleasing to the eye.
Steaming Bay Slabs Complete.                   8th April 2010

Over the last couple of weeks Keith Fairman has made a brilliant job of laying the remaining paving around the steaming bays, a job no-one seemed to want to tackle.  Laying these heavy slabs is not a job for the faint hearted, but in sorting this out, Keith has made this area much tidier and safer, and we can now finish the landscaping here.
Fruits of Winter.                               28th March 2010

The winter of 2009/10 was the coldest and longest for some time, and with all the water disconnected due to frequent frosts, very little was done on site.  However, modifications for the traverser were being thought through, and Dave Ashwell was busy machining big pieces of steel for this in his workshop.
The result is pretty much as the attached photos; the traverser top has been fitted with flange guide rails, and hinged end ramps that taper down to the track; Dave, Ron and John Underhill having toiled on this.  Hopefully the ocassional problem where loco drain cock valves have been damaged due to the height difference has now been resolved.  Importantly a wooden back plate has been added to ensure locomotives cannot fall off the back edge.

Each hinged end plate can be latched up to allow the traverser to be moved, and is counter-balanced to stop it dropping too quickly.  Underneath, a pair of dampers have been fitted to reduce the chance of a hard landing when the traverser approaches the spur line.
|
 |
|
 |
2009 - A Year of Consolidation.
With the track, turntable and station in place, we started the year with a working track and could run trains.  However there were still many big tasks outstanding.
As spring approached our Ted took delivery of some more rail, and after some machining work, Dave, Ron and John got busy laying the extra pair of 7¼" rails.
In pushing ahead to our 'official opening' Rob organised the building a halt at the summit of the site, and work was put into grass seeding areas that had not taken, along with other shrub planting.
One of the essential elements that successfully came into play this year was the ride-on mower; taking a little over an hour to keep the bulk of the grass in check.
In mid summer, we had our "Official Opening", a very successful event somewhat in the spirit of the original track opening some 60 years before, with a celebratory sponge cake.
A good turnout of locomotives, a roaring bar-b-q and decent weather meant an enjoyable day for the 120 or so members and friends attending.  Unlike the 1948 opening, the restricted location and tenancy conditions meant this was not such a public occasion.
Now we have a decent track, many members are busy finishing off models, and several locomotives have been puchased from outside, so there is quite a variety of models within the membership.  Still time to get involved and give us a hand - and get working on your own new locomotive !
Our construction diary is in the adacent column . . .
Please hover your mouse over photos for a description.
|
 |
|
 |
Boxing Day Ice Sheet.           26th December 2009

The season extended right through, regular running until the middle of December.  However, arriving at the track on a glorious morning for our 2nd planned Boxing Day steaming, we found the lower car park / unloading area, steaming bays and platforms covered in treacherous thick ice, the effect of being in a winter frost hollow.  There was no way to safely place a locomotive on the track, so the stalwart attendees enjoyed a few warm mince pies, before abandoning the event.
This was a long very cold spell during which water froze in the pipes from the tank supplying the track.  All pipes and hoses were subsequently disconnected until near the end of March, and no damage was sustained.
Some fresh Concrete work.           21th September 2009

In the midst of a glorious dry autumn, a perfect sunny Monday brought five members together to pour concrete for the top and bottom bridge pads.  Dave, Ron, Colin, John Trott and David Brothwood soon had the bases mixed, poured and gently drying out.   Some of the soil previously dug out has been formed into an additional shrubbery bed behind the station.
Start of the Bridge Build.           8th September 2009

Kicking off the autumn works programme, Tuesday saw the start of earth works for the new footbridge, to connect the top car park to the central area near the steam bays.  Working to Dave's surveyed marking out, John Trott and Graham Walker dug out the banks and foundations, distributing soil to dips around the site; meanwhile Ron sorted out some shuttering.
All rails now laid.                           9th May 2009

Quietly and without ceremony, the final outer rails forming the 7 1/4" track were laid by Dave & Ron on Wednesday.  They then proceded to resolve the timing problem on the ride-on mower, which is now running better than ever.    On Friday, Ted, Derek, Keith, and John U spent the morning laying a second series of large slabs in the steaming bays, although we are short of a dozen or so 3' x 2' slabs to finish it off properly.
Another great topping.                 3rd May 2009

Working to complete jobs ahead of the official track opening, the May boiler testing day was also the opportunity to do a little more work on the 2nd station.  On this sunny morning, concrete slabs were laid on the block wall to form the top, before joining in with the afternoon steam up.
April Showers.                     28th April 2009

Famously April, after two weeks of great weather, the time planned for some work brought a heavy hail shower.  After sweeping away the pooled hail and water, Geoff, Gordon and Rob got on with laying the block base for Riverside Halt - almost a river itself at one point - fortunately a drier evening followed.
Work comes to a Halt.                 13th April 2009

Off site, Roger has nearly completed construction of the new traverser.  On site, at the top end of the circuit, a start has been made on the strip foundations for a station Halt; this will be a safe stopping point for passengers, and a good place to check the water and fire after the long climb.
After a period of rest.                 9th April 2009

The start of the year was fairly dormant, allowing members to concentrate on loco building.  However the last few weeks have seen the work programme pick up.  Rob has planted another 20 shrubs around the site, which is greening up nicely, and the fallout from winter storms has been tidied up.
Off site, all the additional rail has now been prepared, and delivered under the supervision of Ted.  On Wednesday Dave, Ron and John U. laid the first of the new 7 1/4" gauge outside rails, a rapid 44 m track length screwed down in just a long morning.
|
 |
|
 |
2008 - The Track is Built.
Perhaps the most dramatic and exiting year of the build, with a lot of enthusiasm ensuring that jobs were going on right through the (fairly kind) winter months.
While Dave Ashwell and Ron Ireland plus support were working on the track, Rob Speare organised and generally pleaded with others to help on the alternate projects including the fairly ambitious station.
A good mix of people, some travelling a good distance to help, meant that progress on some major items like the turntable base, and traverser bases were ready in time.
The meeting night at the end of May was our first evening at the track site; but that afternoon had very heavy continuous rain.  This stopped around 6.30pm, and those that ventured down to the track found a vast area of the site under water, with a fast flowing torrent rushing down the valley.  Fortunately no damage was done, and in some ways proved the suitability of mounting the track on poles driven into the ground, which would not easily be undermined by running water.
Once the rails starting to be laid, but ahead of the track being complete, Peter Parkes had the priviledge of running the first loco on the track, steaming his GWR Pannier tank No.1761 under the dubious excuse of testing the gradient, which of course was fine.
Dave and Ron made rapid progress with laying the 5" and 3½" gauge rails, aided by some good weather, and towards the end of the summer 2008 we once again had a place to run our locomotives!
The track as built is close to 1000 feet in length.  Initially the traverser was recovered from the old Sandringham track and reused, but it was suffering badly from rust and after a redesign a new one was built by Roger Smith has been substituted.
Although clearly not completely finished, those heavily involved in the construction felt it right to have a celebration, as the track completion also co-incided with the Society's 60th anniversary.  So we had a special steam-up at the track, and Rob produced an iced fruit cake suitably decorated for our 60th Anniversary, with the shape of the new track iced in red.
Our construction diary is in the adjacent column . . .
Please hover your mouse over photos for a description. |
 |
|
 |
 |
End of a great Year.                 31st December 2008

After the hectic summer activity, the Autumn schedule was lighter, but the whole track has been checked and re-levelled by Ron & Dave.  This gave the first chance for many years to enjoy a Boxing Day steam up, attended by three locos in steam and over 20 members and families.

Rounding off a year of building activity, Robin & Rob returned on the 30th December to build the fencing on the outer platform side of the station; 4 hours later on a cool but dry day they finished the job as shown.   The previously sown grass seed has taken quite well.   A few days before, the inside of the Club-house had a thorough tidy-up.
Our Parking Sorted.                 28th August 2008

After the August bank holiday, our Contractor (Courtier) returned for a day, bringing the remaining 100 tonnes of road stone themselves (using 4mm slate scrapings).  They made a great job of the 'middle' car parking area, so we should have a decent capacity now, but means a clockwise direction around the loop road.  The frequent summer rain has enabled the grass seed put down a few months back to take, and once Ron had spent a few hours on the mower, the site looked fantastic.
More like a Station.                     26th August 2008

While the freshly deposited soil was still uncompacted, David and Maurice spent a couple of hours on Saturday morning turning the patch adjacent to our main station into a contoured area, which was later seeded.  When grassed this should provide an area for sitting, embarking, and perhaps popping up a temporary gazebo next to the station.

Meanwhile Robin Drew got on with fixing posts to the rear walls of the station platform, and after Rob cut up a quantity of stakes, Robin and son Harry built an aesthetically pleasing safety fence.  Enhancing this further Rob added a pseudo barrow crossing, which forms a safe step off the sloping platform, and some yellow lines on the platform top; starting to look like a station now.
The Digger Returns.                     22nd August 2008

The tail end of July and first two weeks of August were wet most days, so apart from the dry July meeting at the track, everyone had a break. Then our Contractor returned with heavy equipment and a three man team.  An important first task was to install a land drain from the station / tuntable area, to the brook.  Then between lorry loads of stone arriving, the digger enhanced and slightly extended the top car park area.

The lower parking area was rolled flat and edged with some more concrete sleepers previously recovered from the Sandringham track; and additional soil was placed in the tidied-up station area.  However third party deliveries of stone were very sparce, a few lorry drivers having difficulties accessing the site, and the top parking area could not be completed by the weekend, when the equipment was due to finish.

With the ground countored, a couple of poles were pushed in by the bulldozer driver Gerry, to allow the car unloading ramp to be built.  Our boys wasted no time in shuttering an extension to the turntable area, so the pole which will become the track end that meets the turntable, can be firmly set in concrete.
Top Finished.                                 18th July 2008

Two further afternoons supported by Gordon, Maurice and Rob, allowed Geoff to finish the concrete top of the station platform, despite the miserable weather in late June and the early part of July.  The remaining tops, slopes and step consumed a tonne bag of aggregate in the concrete mix.  Meanwhile Dave sorted out 2 irritating slow punctures on the mower, now in regular use.

Ron has fitted the test track with buffer stops, the one at the turntable end can be discretely hinged over the end of the track to allow access to the turntable.  Hopefully this should prevent accidents with runaway locos while testing.  Also the site has been grass-cut, strimmed, and Dave has toiled to remove ragwort weeds that have invaded the the wilder parts of the site.
Meeting Steam Up !                         30th June 2008

In sharp contrast to May, the June meeting held at our new track was the first to have a loco in steam.  A good turnout, and many were able to ride the track for the first time as Pete steamed his pannier loco once again.  But no time for celebration yet, there is some work to do on correcting cambers and dips in the track; nevertheless this was deemed a succesful evening.

With the experience of the May club night flooding still freshly in mind, a small team got stuck in on the Satuday morning after the meeting to dig the remainder of a relief channel to stop water in the adjacent field building up and overflowing into our top cutting.  A few roots and other obstructions have also been removed to ensure the brook runs freely.

This followed the installation of six steaming bays, each provided with a 12v power supply.  The traverser is being temporarily re-used while a new one is made, suited to this site.  In time the adjacent area should be paved, the club was donated some large re-usable paving slabs, brought to site by Ted, Derek and James.
Ring of Steel Completed.                     18th June 2008

Having made fantastic progress with rail, fish-plates, countless sleepers, and even more screws - Dave & Ron completed laying our circuit of track, and the 'test spur' on 13th June, well over 1000 feet in just 5 part weeks - and it looks very good.

Our dynamic duo have also assembled and made ready for use a toilet in it's own housing, complete with light and ventilator - the first time the Club has been able to provide such a facility, which will be appreciated by many.  Work now turns to the steaming bays.
Behind the Scenes.                               8th June 2008

The May club meeting was the first in this year's calendar to be held at the track site.  In the 2 hours prior to the meeting, Newton Abbot saw some reasonably heavy rain, falling on saturated ground.  Those who ventured out to a sunny evening witnessed a sudden and unexpected flooding of the site's central area.  No track damage occurred, and we can now plan defences.

As track laying progressed, the first week of June was busy with lots of members involved; a start was made on a new flood prevention ditch, rail was prepared, sleepers moulded, rubble loaded, and water crane parts sourced.  On Saturday 7th, dodging some heavy lightning showers Geoff, Jeff, John and Rob added ends to the first platform, while Pete ran the mower around.
Clearance Testing.                               21st May 2008

The 4M turntable, one of the jewels of the track is now complete and ready for service.  Ron has designed an interlock to the various 'roads', operated from a centrally placed lever accessible from either side.  The length allows a loco + trolley to be turned, reducing delays on the mail-line.

By invitation, under the auspices of 'checking the clearances' Pete managed to get the first steam up on the part circuit.  Appropriately his loco '1761' is an original 'Newton Abbot' build, although it was sold and has travelled over the last 40 or so years, before coming into Pete's hands.  He reported that the gauge widening seems just right to allow free running on curves.
Beset by Water.                               18th May 2008

This week brought the worst thunder and lightning storm for many years locally, with torrential rain.  This took it's toll on our access road where cascading water carved many deep ruts.  But the additional rain on Friday night burst through from the adjacent field; a continuous flow of water entered and followed our top cutting, flooding over 1/3 of the sites.  A relief trench will be required urgently to divert this and future water away.

Meanwhile on Sunday, with Rob having built up the remaining rear station walls, and following a lot of rubble gathering, the first piece of platform top was poured; Alan mixed the concrete as new member Geoff poured and floated the new surface, forming the the centre part of the outer platform.
The Start of Track-Laying.                         8th May 2008

Clearly influenced by too many hours looking at Triang Hornby catalogues, Rob's station design capitalizes on the track height to include separate raised platforms.  Here Rob inched it closer to completion as the cut sloping ends were cemented onto the walls, and by adding the inner facing step base.  The voids now await filling with rubble before concrete tops can be poured.

On Saturday Ted delivered a batch of 300 sleepers, so track laying now commenced in earnest, the rails are being laid with staggered joints to minimise any kinking.  By the end of a hot Wednesday over 30M of track had been laid by Ron & Dave, virtually 1/10 of the total track length.  For this, battery powered screw-drivers, and spare re-chargeable batteries have proved essential.
Building the Platform Walls.                     4th May 2008

Following a very showery April, the first Saturday in May saw a small team assemble to build the platform walls.  With Jeff busy at the mixer, Alan and Geoff built up the block walls while John & Rob kept materials at the ready.  During the day John Bradley a model engineer visiting the U.K. from South Africa paid us a visit, he'd been following the track build on the web-site.  By 4.00 p.m. the bulk of the two block high outer walls were up.
Arrival of the Sleepers.                           30th April 2008

There was a huddle at the back of the April club meeting as Ted brought in the first batch of freshly minted sleepers, from his new injection moulding tool.  Long awaited, some delay was caused by finding the right material, polypropelyne was not sufficiently strong; and finally polycarbonate was chosen, giving a tremendously robust sleeper.  The wood grain effect sleepers have recesses and prepared screw holes to locate the flat bottomed steel rail, laid initially for 3.5" and 5" gauges, with the provision for 7¼" gauge rails to be added later.  The following Monday, Dave & Ron were building the first piece of track on the turntable; the finished result looks fantastic !
Platform Foundations.                           13th April 2008

A showery morning greeted Saturday's 8 man team.  Whilst David, Maurice and John did some tidying up of the site, the key focus was on digging foundations for the station platforms.  Alan had prepared a clever device for gauging the levels relative to the track, and the foundation trenches were dug by lunchtime, encouraged by a heavy rain shower.  After lunch the big generator was fired up and Jeff, Robin and Maurice got busy making concrete, while Alan tamped it to height - a successful afternoon.
Provisioning of Services.                         3rd April 2008
Despite a cool and wet end to March, work has progressed.  Ron installed the turntable's interlocking latches, and it has received a new coat of paint.  Also, a water line and power cable have been pulled through previously laid conduit to provide services for the steaming bays.  Plans are now being drawn up for the Station platforms, and for grass seeding some of the site.
The Turntable Lands.                             22rd March 2008

Following on from concreting the traverser bay, it was time to install the turntable.  Despite its size the installation was easier than expected just taking 3 people to put it in place.  After checking it worked as expected, and finding the true centre, the concrete base was drilled for fixing bolts.  The turntable has been finished to blend with the rest of the track, though is still awaiting the locking latches as designed and built by Ron.
The Big Mix.                                     3rd March 2008

As we enter the Society's 60th anniversary month, the last 2 weeks have seen much progress.  Ron & Dave have checked the whole length of the track base, straightening where required and tightening and fitting additional screws.  Between them Rob and Pete planted 5 more trees, and off site much of the rail has been prepared and drilled by Ted, Derek, Richard and Jack.

But the major event was the concreting of the traverser base, on another glorious day, making up for last year. On 1st March, a team of 8 including Alan, Jeff, David, Robin, Graham, Roger, Jack and Rob worked together well, and the whole area was completed with a tamped finish in the day, with just 1/6th bag of aggregate and 1/2 bag of cement over.  This can now be left to dry out thorougly whilst the turntable is put in place.
Shuttering Done.                         16th February 2008

So far, 2008 has surprised us with kind weather, and again on this Saturday we were able to get on with important tasks. A team of 4 spent several hours preparing ground at the top of the site, smoothing dips and bumps left by the bulldozer, while inside the club-house the turntable latches were being fitted.

But the main activity centred around a team assembling Alan's prepared timbers to form sturdy flat shuttering for the traverser bay.  Full length 70mm x 51mm timbers will be cast in, to be removed afterwards forming a recess for the traverser running rails.  The base has been filled with breeze blocks recovered from the old track site.
Next the traverser.                       13th February 2008
With just a quick breather the next goal is a base for the traverser.  Roger has almost cleared the old track site and delivered about 2 tons of concrete blocks, and further old blocks were delivered by John T, to act as a rumble base for the concrete.

Meanwhile Alan has been preparing heavy shuttering for the base which is 9m x 2m with slots cast in for the rails, and tubes for electrics.  The area is already partly dug out and has now been pegged, and on Feb 16th a working party will finish digging, and erect the shuttering.
Dave has drawn up the paving plan while Ron is starting to modify the traverser recovered from the old site.
Concreting at last.                       26th January 2008

We could not have wished for a better day on January 26th - warm, dry and sunny (sorry Scotland), as a working party of 15 members tackled four different jobs.  The approach road was cleaned of mud, the small spoil heaps dug out from the turntable base were redistributed to fill in dips, and the big generator refurbished by Keith was returned to site and connected - and to much delight we now have working lights and power sockets in the clubhouse.

But the main event was the concreting of the turntable base, which had drained of water.  After some additional preparation which included placing many broken up concrete blocks in as a base, the concreting took just over 4 hours of continuous mixes.  This sturdy platform is the result of a great team effort.  The only casualty of the day was my Rob's car suffering a complete battery failure on site, so it was a quick exchange with the lawn mower battery to get home.
Turntable Excavations.                   12th January 2008

On this amazingly pleasant morning Alan, Jeff, John and Rob tackled digging out and shuttering the base for the turntable.  The very wet soil was becoming quite chewy by the time digging was finished, and as it then started to rain for the weekend, the next day it became a boating lake !
|
 |
|
 |
2007 - A trackbed takes shape.
Having argued about the shape of the track, the time came to build it.  At near 960 feet in length, with a rise in levels of some 3.5 metres from end to end, much attention was paid to ensuring gradients would be within the capability of most locomotives.
The long valley site requires a fair rise from one end of the site to the other, and the uphill gradients will be testing, different according to the direction being run.
Setting Out and Construction
Once the final design was arrived at - mainly derived from Dave's computer design that showed the gradients, the whole site was pegged out to match the computer design, marked for height as the top area would require further excavation works.
Special note should be made of our curved turntable, built into the curved track which allows us to take locomotives to the steaming bay within the track.  The design was drawn up by Albert Way, then neatly welded up by Ces Courtney.
This was created at 4M long to ensure a loco and trolley could be brought onto the track together, to minimise the disruption to trains already on the main-line, and in practice has has worked very well.
Our Chairman also decided he would include within his sleeper moulding, the opportunity to add a pair of 7¼" rails later, which would allow trolleys with greater stability to be used.
We are very grateful to a number of members who offered, then donated the bulk of materials for the track construction, supplemented by gifts of money from some others.  The generosity of these members is really appreciated.
|
 |
|
 |
 |
Deep in December.                   26th December 2007

Keeping up the pace, Dave and Ron were on site on a dry 22nd December, along with one of our neighbours and his bulldozer.  Within the morining they had remodelled the parking area; extended the length, pushed back the spoil heap, and built up the edges.
Also during the week John T. ferried more old track and other items away for recycling.   A fantastic job done, but with less than 3 months to the 60th anniversary we are hoping for more good weather in the new year.
Winter Working.                       15th December 2007
Despite turning slowly to winter, there is still plenty of activity. A third Sunday morning effort allowed more sleepers to be recovered from Sandringham track site, a total of 42 for re-use.  Much of the old rail from Sandringham has been taken away for scrap, but some site tidying and a tip run is still required.
Keith is doing a grand job refurbishing the large generator off site, whilst Ron has rebuilt the steering gear on the mower.
On site, Dave has wired the club house with a fully protected ring-main and 4 fluorescent lights, whilst Ron has given the turntable a coat of primer paint.
Turntable assembled.                     17th November 2007

The previous weekend saw John T And Tony J remove the last of the soil mountain by hand, by all accounts enjoying the beneficial exercise !
Dave has repaired the electrics on the mower so hopefully it should now charge the battery.
On Saturday the curved turtable was assembled on its base for the first time indoors, and it not only looks stunning, but rotates very smoothly with just finger pressure; brilliant !
Season continues.                           4th November 2007

The good pace has continued with the kind autumn, and using a hired mini-digger and dump truck the steaming area and traverser bay have been excavated.  Working for 7 days Dave & Ron also moved the bulk of the excess soil from the upper parking area to raise the level elsewhere; followed by members levelling the dumped spoil manually.
A good turnout on Sunday 4th allowed us to retrieve 14 (full size) concrete sleepers from the old site, each is a 4 man lift.  So far, these have been used as road kerbs, and will be secured with long rods.  Keith has volunteered to refurbish the generator and this has been taken off site.
Turntable welded.                           17th October 2007
Ces completed welding of the steel turntable today, the impressive 4M structure now needs painting.   At the old track Graham and Roger have completed lifting of the rails; when various items have been moved to the new site we can terminate the old site lease.
Derek has started infilling the bottom of the lower cutting with gravel laid over sheeting, to act as a weed suppressant.  An old ride-on mower aquired by Rob has arrived on-site; although requiring a little attention, this should help keep the site presentable once seeded.
Boarding completed                       12th October 2007

The extended summer has meant warm days at the track site.  Today - Ron, Dave and Derek finished erecting all the raised trackbed and steaming bay spur line, including fitting all of the intermediate spacer blocks, and setting cambers.  Assembly of all the timber work has been achieved in a little over two months, and has emptied the club house of the stacks of planks and blocks.
The turntable has been welded up by Ces, though there is some finishing off to do; quite a heavy fabrication.  The next job will be sorting out a solid foundation for it.  Elsewhere Rob has built up some embankments and planted the first of a series of trees, both to enhance the site and to ensure our activities are carbon neutral; this compliments the planting being done by Pete in the steep embankment in front of the Club-house.
Progress Maintained.                       29th September 2007

The kind September weather has allowed for Dave and Ron to continue assembly of the raised track bed past the summit of the track.  Half of the total length has been erected, and they hope continue while we still have good weather, and the ground is not to soft.  A successful Saturday working party tidied up some ground and the new car parking area, and sorting out a permanent base for our water collection tank.  This weekend will see another Saturday working party, and a team is due to be assemble and weld up the 4M long turntable.
Summer at Last.                       11th September 2007

The July Club meeting was held at the new track-site, and was the start of numerous regular working parties, as finally the weather settled down.  Within days, some raised track support was assembled, Dave & Ron's team working out the best way to do it, while a Friday evening group dug out floor of the top cutting and remodelled the walls of the lower cutting.  Meanwhile the cement mixer has arrived, and the pre-cut steel pieces to construct the turntable have been collected.

Preceeded by a full strimming of the site, the major event on the weekend of 8 & 9 September was the return of the digger, and a fair support of members (despite clashing with the Ascot 100th M.E. exhibition).  This tackled the remaining earth moving jobs including slight lengthening of the ditch and remodelling of some areas, resulting in the site being quite transformed.  All the remaining track support poles, and those for the steaming bays are in place, and being cut to length.  Access for cars has been improved, and an additional car parking area has been excavated; but the site will need a measure of hand raking to smooth out the dips inevitably left by the digger.  Fantastic progress !
Consolidation Inside.                       30th June 2007

Despite the enormous amounts of rain we've had, the dug out brook has worked well, and we have not suffered flooding acros the top of the site as previously.  We're still waiting for the digger to return, and a cement mixer to be delivered, so really only strimming and weedkilling has been done externally in the last few weeks.

However, much activity has taken place inside the club-house.  The bearing for the 4M turntable has been prepared, converted from a lorry axle hub; and a team have bolted the pre-drilled blocks on to the top hats - these are now ready to slide on top of the track poles.
Poles installed.                                 22nd April 2007

While on site, the mechanical digger formed a new cutting at the top of the site, which will help to keep the gradients reasonable.  It was then used to push in over half of the tubular track support poles, which have since been marked and sliced to the correct height.  During the month the tanalised treated blocks were sent for treatment, then collected from the saw mill and returned to the club house.
Major Work Achieved.                     5th April 2007
What a week, what progress !  With the core team of Dave, Ron and Derek, supported by other members, all the timber blocks for track support have been sawn up and drilled ready for treatment. In addition the digger arrived on site on Wednesday, and the skilled driver soon had the brook dug out to the extent allowed at this time, plus a further small cutting, and ground levelling.
Work Commences.                     31st March 2007
During the week thick timber beams and steel tubes for the track support were brought to site, and on Saturday afternoon at short notice, seven members arrived to start cutting up blocks for the track supports, using a power saw and portable generator set up in the club-house. On completion, these blocks will be sent away for pressure tanalising.
Preparation Work Commences.         24th February 2007
The construction methods have all been agreed, and a modified route requiring almost no further excavation work has been selected by the Committee.  All materials are being ordered and preparations are being made for a production line of various components in the club-house.  Cutting back of shrubs near the track path was carried out this week.  We have the official route for the site ditch to be excavated to drain the field, but it is just too wet to bring a digger on site at present.  It will all start soon.
|
 |
|
 |
2006 - A design comes together.
The initial design for a track on the site was worked up by Ron Ireland, following the terrain contours of a site map; at this stage the site was very wet, quite overgrown, and we did not have a detailed survey of our own.  The track was estimated at 960 feet length, and included two rail bridges to cross the water course adding interest, intended as opening sections to allow Council maintenance equipment to go inside the track area, to keep the brook clear; and a few variations on this were proposed by other members to maximise the site use.
However, due to a number of factors, the Committee later decided on a slightly less ambitious scheme with a narrower track footprint, removing the need to bridge the brook with opening bridges, which could be expensive.  This would (optimistically) also allow the Council a 2m wide access to the brook for a small digger to keep it clear.  This compromise did cause some bad feeling at the time.
The valley shaped site requires a fair rise from one end of the site to the other, and the design that emerged has some testing gradients, particularly if running anti-clockwise.
The intention was to build a raised track, from all new materials, dual gauged for 3½" and 5" gauge locomotives.  Included in the brief were steaming bays, with a trailer off-loading spur, serviced by a turntable.  Also it was deemed a Club house would be essential (something we had never had), initially to be used as a site office and materials storage.  A future bridge could cross the track to allow traction engines to drive to the arena in the central area.
A lot of thought went into trying to make the track easy and quick to construct, and without the need to mix mountains of concrete for pillars.  In the end it was agreed to use scale secion steel rail, screwed down to purpose made plastic sleepers (to be supplied by our Chairman who is in plastics), supported on twin longitudinal timber beams,
in turn bolted to galvanised steel posts pushed into the ground, set in concrete where required.
By this time a track design team had been put together, but in order to be able to understand the site properly, Dave Ashwell bought a theodolite and surveying poles, and set about plotting the track site on his computer.
|
 |
|
 |
 |
Club Hut Secure.                     11th November 2006
Tim's team has now fitted secure shutters over the windows as a security measure, better to be cautious than risk a break-in.  The hut is slowly accumulating benching to provide workshop facilities for the track construction.  Some soil testing has been carried out and pretty much the whole site is quite soft, having been frequently saturated, and will affect the way the track is supported.  Dave's team has started pegging out the track shape, transposing measurements from the design done in Turbo-Cad.
A Building Rises.                     16th October 2006

Monday 16th saw a number of members arrive early on a warm but overcast morning, to monitor the manufacturer's two-man team assemble our new hut.  Members also installed drainage to take away rain water accumulating behind the hut.  Despite a brief thunderstorm, work was complete by about four o'clock and the building was left watertight and locked.

Some windows may be re-positioned to ensure good ventilation and one member will be making shutters to protect the glazing from intruders.  This is the first real club-house the Society has had, and it will be fitted out with a kitchen area.  For now it will be needed to store construction materials.
A Solid Foundation.                     10th October 2006

At last some tangible work has been undertaken on site.  The concrete slab base for the new Club building was poured on 30th September, followed by the wettest weekend in months !  It dried out o.k. and is ready for the building to be delivered and assembled.
Finally some Agreement.         21st September 2006
Following what seems like an age, and intense negotiation over the fine print of the site Lease we finally have agreement; and after chasing (threatening), we have planning consent for the Club building.  This has enabled us to place an order for the new building which will be essential for storing materials during the track build.  Hopefully the concrete base will be laid and the building assembled (by the Supplier) during the early part of October, if the weather doesn't collapse.  Then we can get down to pegging out the track.
More road-works.                     17th July 2006
After two weeks of exceptionaly good (& hot) weather, Dave's team has continued cutting back the overgrown areas, removing boulders and fallen branches, now nearing completion.

The Society has dug deep and re-employed the Contractor, who came back on 15th July and rolled in 90 tonnes more harcore to finish off the roadway, ensuring site access is safe in all weathers.
The next job will be to decide on the club house and prepare a foundation, we really want this up before the summer ends; and to peg out the track route.
Movement At Last.                 24th June 2006
After weeks of wrangling; finally the Council's contractor came back to site this week to form the lower roadway onto the field, and to move some of the heaped soil to allow more parking area. An area for the base of the club-house has also been cleared.  The Club has had to share the cost of this work, but one member has personally paid for around 40 tons of hardcore to form the road to the club-house area.

Dave, Albert and Derek wrestled with cutting back a lot of the scrub that has grown since the field has become unattended, and chain-sawed much dead-wood.  The owner of the adjacent field also kindly brought in his tractor mounted mower, and the area is looking very good.
Progress Update.         23rd April 2006
Spring now firmly with us, but still no sign of the brook being dredged.  Much work has been done by Dave Ashwell to plan for acceptable track gradients.  The Steering Group is due to make a presentation of the current thinking to the Club's April meeting.  The Society has been awarded a Grant which will probably be used to purchase a building, to provide a store, and later a club house.
Permission Granted.         22nd March 2006

Another site visit was made by Dave and Derek with the Council engineers.  Clearing of the top end of the brook should be done by the end of the month; this should allow much of the ground to dry out. Permission to start on site was given on March 15th.  However our construction will need to start at the top part of the site as there will be substantial engineering works to the culvert for a number of months.
Site Visit.         27th February 2006
The Track Committee assembled at the track site on Sunday 26th, very cold.  Dave and Chris' survey of site heights makes the gradients look acceptable.  Very wet underfoot after the previous week's rain, and we hope the brook will be dredged soon.  After discussion, some re-pegging of the track route has been marked, following concerns over potential flooding of deep cuttings.  Awaiting permission to start on site.
Drainage.             13th February 2006
The Contractor returned to the site, and installed additional drainage to the new access road, but since then we have had little rainfall.  In fact it has been so dry that the 100 or so shrubs planted by the Council on the slope adjacent to the access road are struggling. The planned clearance of the watercourses has still not started and we're unclear when it will start.
The track steering Committee has met and considered many aspects of the site; and the track construction method has been agreed.  The next stage will be a site visit to double check the gradients and exact track route.
|
 |
|
 |
2005 - The need for a new Track.
From 1988, the Society's third raised track operated in Sandringham Park, Newton Abbot, and served us well.  But increases in vandalism and interference to the track and operation, noteably after an adjacent skateboard park opened, caused much extra maintenance, often involving repair by the same one or two people.
Sadly, this also deterred some members from taking their locomotives to the track except during a week-day when most children were in school.  During a weekend's steaming in 2005, some of the children to whom the railway was giving rides conspired to place items on the track, derailing Keith's locomotive, which sustained some damage.  As these miniature locomotives are the product of many thousands of hours' work, owner's reluctance to invite problems is understandable.
Click here for some details of track damage.
But contrastingly with our membership now being drawn from a larger area, were many in the process of constructing new locomotives, who wanted a safe track on which to run.  Other Society members own traction engines or steam rollers, and the membership voted at the AGM to find a new location which suits all our needs better.
During 2004/5, Derek Yates spearheaded the search for both funding and a more secure location.  Sites at Ipplepen, Dawlish Warren and even Exeter were given serious consideration, but all were eliminated.  In the Spring of 2005, three members of the NADMES Committee had a meeting with the Chief Executive of Teignbridge Council in our pursuit of a new location for our track, and the need for operational safety.  The search was stepped up and a few more possibilities were identified.
In mid-summer, initially shrouded in secrecy, a site was identified - land which the Council was in the process of buying to allow access to a huge culvert required for highways maintenance.  Since this area is liable to flooding, and forms part of a water storage scheme, it was unsuitable for housing but fine for a raised railway.  Importantly, it's away from close proximity to housing, playing fields and skateboards.
Members of the Committee were consulted, and following a survey, Ron Ireland worked up a provisional track plan based on the demanding site gradients.  This more private site would allow for an increased length railway track and a central traction engine arena.  Although the option of a ground level track was mooted, very few of the membership owned a 7¼" gauge locomotive, and the majority preference was for the raised position.
As Ron had been very involved in several repairs to the Sandringham Park track, he was very keen that the track should be easy to build and easy to maintain.  A number of members visited the Taunton Club track and were pleasantly surprised by the stability of the wooden plank system, and Ron's design for our construction is a reworking of that principle, without the use of concrete support piers.
Planning consent (for the whole scheme) was granted in mid November 2005, and Contractors moved in to create an access road for Council maintenance vehicles, which we could also use.
The Council's Contractor finished installing the initial stage of the access road by the beginning of December 2005.  Whilst the Tenancy agreement was being finalised, the Society pursued grants and other funds that might be available to us to create this facility, appropriate to the 200th anniversary of the birth of Brunel (2006), in an important railway town.
As a brilliant opportunity for the Society, and funding pretty much in place, it was a case of pooling the enthusiasm that had been generated and getting stuck in !
Our construction diary is in the adjacent column . . .
Please hover your mouse over photos for a description.
|
 |
|
 |
 |
Access Road.       20th December 2005
During the latter half of November 2005, Contractors created the new access road.  This is to allow Council vehicles to access the watercourses, and the culvert under the dual carriageway for maintenance.  During December the site was very waterlogged from heavy rain as indicated in the photo.

We are looking forward to working in this lovely setting, and foresee this as a fantastic amenity - worthy of the Society's energies. Through this we can safeguard model engineering interests in our community for many years.
|
 |
|
|
|
|
 |
 |